Primary Electrical Improvements
About this Project
The Step 4 project provides the addition of new 12kV Substations and completes the installation of a 12kV out power system loop including the addition of supervisory control and data acquisition (SCADA) system controls. The scope of work includes: Installing 12kV switchgear at University Substation; Constructing a new 12 kV South Substation on the outer campus utility loop; Installing a new 12kV feeder from University Substation to South Substation; Providing a new 12 kV feeder and duct bank system between South Substation and East Substation; Replacing East Substation and Central Plant CP1 and CP2 switchgear protective devices; Replacing cogeneration MV-01 switchgear relay protective devices; Providing an entirely new 12kV SCADA system; Installation of SCADA system hardware, programming and communications at each substation; Interconnecting substation SCADA systems with redundant communication systems; Replacing existing Rule 21 protection system relays and PLC interface.
Status
Projected Completion:
February 2018
Project Phase:
Completed
Last Updated:
03/30/2022
Project Details
Project Manager: | Jeet Singhal |
Design & Construction Team | |
---|---|
Gen. Contractor: | Helix Electric |
Architect: | Mithun |
Struct. Eng.: | DCI Engineers |
Civil Eng.: | KHR Associates |
Mech./Plumbing Eng.: | Hartford Engineering |
Electrical Eng.: | Michael Wall Engineering |
Landscape Architect: | Mithun |
Sub-Contractors | |
---|---|
Electrical: | Helix Electric |
Waterproofing: | Angelus Waterproofing |
Steel Fabrication: | Advanced Welding |
Masonry: | Masonry Concepts |
Earthwork: | HMS |